Delays in acquiring land posed problems for Delhi Metro phase-III project
|
|
|
|
Top Stories |
|
|
|
|
SME Times News Bureau | 20 May, 2019
Delays in acquiring land, getting No-Objection Certificates besides
other unanticipated hurdles plagued the third phase of Delhi Metro
project, leading to time overrun in expansion of the national capital's
modern transport system.
The phase III of the project was
scheduled to start in May 2011 but first construction could begin only
in January 2012 and a small section still remains unfinished. It is
likely to be completed by the year-end.
Unlike this phase, land acquisition for the first phase of the Metro project posed no problem and was carried out smoothly.
Among
the challenges, a major one was land acquisition since the new Land
Acquisition Act was in place during this phase of the project which made
it extremely difficult to acquire land as the machinery to be put in
place to implement this act was still not in place and compensation
levels were also expected to be much higher, said Anuj Dayal, Executive
Director of the Delhi Metro Rail Corporation (DMRC)..
"In
comparison, in the earlier phases, DMRC was able to acquire the land
needed for the project reasonably smoothly under the provision of the
Land Acquisition Act, 1894 with the help of the state government and
good judicial support. DMRC, thus had to acquire private land in Phase 3
through direct negotiation with individual landowners which was a
difficult and time-consuming process," he said. AA
Dayal said
land acquisition issues have often delayed Delhi Metro's pace of work,
but the DMRC team has always worked hard to make up for the lost time
and completed its projects within schedule.A
Initially, the third
phase of the Delhi Metro project was supposed to be only 103 km long
but gradually its size increased with the Metro going to various parts
of the National Capital Region (NCR), including Bahadurgarh, Ghaziabad,
Noida, Ballabhgarh, among others, which made the whole project about 160
kms in length, he said.A
"On multiple stretches, land could not
be acquired and the contractors could not begin work. There were
stretches where the necessary land for construction work could not be
arranged on time. These areas were the Chirag Delhi Metro station and
the Kalindi Kunj depot," Dayal said.A
A similar issue was also faced at the Okhla NSIC Metro station where it took a delay of about two years in acquiring the land.A
"Initially,
the Okhla NSIC station was part of a package of six elevated stations
from Okhla NSIC till Kalindi Kunj. However, work began on all other
stretches in December, 2012 while the Okhla NSIC station's work could
not be started due to land acquisition delays. Therefore, when the land
could be acquired two years later, it was brought out of the purview of
the earlier contract package and a separate exclusive tender for this
station was floated."A
The location where the station is located
had a few handloom and artefact factories. There were about six
occupants who ran their businesses from that location.A
"The
occupants (both owners and tenants) of that area were convinced that an
additional floor would be erected above the station premises and they
would be allotted space there (though only on payment of the
construction cost). This decision also helped a lot in avoiding lengthy
legal hassles and at least the construction work could be started," he
added. AA
"All these corridors, in public perception, were always
seen as part of Phase 3, though many of these extensions were
sanctioned in the later stages. Thus seen in an overall perspective, the
volume of work involved in Phase 3 actually almost equalled the total
work which was done by the DMRC in phases 1 and 2 put together in 12 and
a half years," he said.
On the Janakpuri West-Botanical Garden Corridor also, unavailability of land posed a hurdle in completion of work.A
Talking
about the 9.37 kilometer long Central Secretariat - Kashmere Gate
corridor, one of the first corridors of Phase 3 on which work began in
May 2011, Dayal said the corridor was completely underground with seven
stations -- namely; Janpath, Mandi House, ITO, Delhi Gate, Jama Masjid,
Lal Qila and Kashmere Gate.
"This corridor is also called the
Heritage Line because it is passing through that part of Delhi which has
a rich historical background with lots of heritage monuments that were witness
to its splendour in bygone days. Some of the monuments falling
alongside its 'alignment are Jantar Mantar, Ugrasen ki Baoli, Khooni
Darwaza, Delhi Gate, Firoze Shah Kotla, Shahi Sunehri Masjid, Lal Qila and Jama Masjid."
He
said this smallest stretch of Phase 3 was filled with the maximum
number of challenges of every kind. Some problems were so unique, which
DMRC engineers had neither anticipated nor faced before.
Goyal
termed Janpath station a challenge, "since the station was situated
adjacent to the extremely popular and busy Tibetan Market at Janpath."
"Tunnelling
close to the Heritage sites like Jantar Mantar and beneath a crowded
market like Janpath was extremely challenging. The Corridor was passing
beneath important buildings like the Eastern and Western Courts, Nepal
Embassy and American Center."
Between ITO and Delhi Gate section,
he said, the first major challenge of this section was the presence of
the 16-century old historical monument 'Khooni Darwaza', constructed by Sher Shah Suri, the then ruler of Delhi. It is located just half a kilometre from Delhi Gate.
"Since
the DMRC tunnel was passing close to this monument, DMRC conducted 24
hours real-time monitoring during tunnelling in that area. The upline
was 17 meters from the monument while the downline was 30 meters from
the monument.
The Downline tunnelled through soft soil and
achieved its breakthrough in March 2014 after constructing 864 meters of
the tunnel.A
"The Upline, on the other hand, encountered Sudden
Hard Rock and it stopped. A team from China was called to break the rock
from inside the chamber of the tunnel, but this exercise was
unsuccessful," Dayal said adding that the DMRC then employed a Pipe
Pushing Technique.A
In Old Daryaganj area, with a number of
dilapidated buildings and structures, the DMRC had to put up vertical
supports in all structures during the tunnelling process.A
"People
also had to be evacuated from these buildings in a phase-wise manner as
a precautionary measure. The people had to be evacuated twice during
tunnelling on both the tunnels. A total of 2,000 people were evacuated
with around 650 people evacuated in a single go. They were put up in
various guest houses situated in the nearby areas and DMRC paid for
their lodging and food expenses. DMRC also repaired and restored their
houses before shifting the residents back. Shifting people was an
extremely stupendous task as they had to be convinced and satisfied
fully before they agreed to do this," Dayal said. AA
|
|
|
|
|
|
|
|
|
|
|
|
|
Customs Exchange Rates |
Currency |
Import |
Export |
US Dollar
|
66.20
|
64.50 |
UK Pound
|
87.50
|
84.65 |
Euro
|
78.25
|
75.65 |
Japanese
Yen |
58.85 |
56.85 |
As on 13 Aug, 2022 |
|
|
Daily Poll |
|
|
PM Modi's recent US visit to redefine India-US bilateral relations |
|
|
|
|
|
Commented Stories |
|
|
|
|
|
|
|
|